Every rollercoaster fan knows what you mean, when you are talking about coaster-bingo’s. A rollercoaster fan has scored a coaster-bingo when he or she has ridden all the rollercoasters in the park what they were visiting. This have to be not only the thrillcoasters but also every family coaster and kiddie coaster. But coaster fans …

Liseberg officially opens Valkyria

August 10, Liseberg opens Valkyria for the public after a 2 month delay in the construction. Everyone was very happy to make a ride on this impressive new rollercoaster.

Testing for Valkyria finally started

After the park had placed the roof of the tunnel, the testing for Valkyria finally started last week. Here is a nice video with onride and offride footage of these tests.

Work on Valkyria’s tunnel continues

At Liseberg the work on the tunnel for Valkyria continues, after the last section of track was put into place last week. The crew is also working on the electrics and the station. Source: https://www.facebook.com/groups/495578810813841/permalink/585330168505371/

The final section of Valkyria track is in place

Last week finally the last section of Valkyria track was installed at Liseberg in Gothenburg. This day was very special for the construction crew and some fans. They were all allowed to write their signature on this last section of track before it was installed. Source: http://www.themeparks-eu.com/news/the-final-section-of-valkyria-at-liseberg-is-in-place A video of this special moment can be …

Firstdrop Valkyria almost ready

After all the trouble they had at Liseberg with the digging of the tunnel for Valkyria. They are now really picking up the pace with setting up the last pieces of track for this rollercoaster. Today almost all of the firstdrop was installed, except the holdingbrake which will be installed this friday. Source: https://www.facebook.com/groups/495578810813841/permalink/577951745909880/

Construction Valkyria experiencing major problems

In Gothenburg the construction of Valkyria is experiencing major problems. Almost all of the coaster steel is erected now, except the part for the tunnel. Because of the very difficult soil in this part of the Liseberg themepark the constructioncrews can’t do the work they wanted to do. The park is currently working on solutions …

Top of Valkyria’s lifthill is placed

After some startup difficulties, the construction of Valkyria is now running very well. The top of the lifthill has been put into place this week. Göteborgs skyline blir lite mer spännande när Valkyrias högsta del är på plats https://t.co/uJ9tmtSVLG pic.twitter.com/FSlp8w3Jax — Liseberg (@Liseberg) 7 februari 2018

First trackpieces for Valkyria are up

A couple of days ago the first trackpieces for Valkyria, the new Divecoaster in Liseberg Sweden was placed on it’s supports. And more pieces are waiting for installation. The construction of valkyria has already been delayed due to the difficult soil in which the tunnel had to be excavated. Source: http://www.lisebergblogg.se/andreas/valkyria/ More construction photos: http://themeparkreview.com/forum/viewtopic.php?f=2&t=46937&start=2680

Trackwork for Valkyria starts in January

The first trackpieces for Valkyria @ Liseberg where already at the park 2 months ago. But now the most important pieces have arrived, the parts for the lifthill. Setting up these pieces will start after the holidays in January Steel will start to go vertical in January. @Liseberg @veilstrup pic.twitter.com/s6pzGX3xol — EuropeanCoasterClub (@coasterclub) 19 december …